Process Simulations

Steam supply

This example shows study of safety and availability consideration of a steam supply system. Steam is generated by several suppliers (orange boxes). The pressure supply is regulated by different reducing and let down stations.

In this particular scenario several consumers trip suddenly (red box, figure 2). The system response is investigated.

Figure 3 shows the pressure change with time in the vicinity of one of the blow-off valves. The pressure reaches approx. 95 bar within 6 minutes. This is an indication of inadequate system control and long reaction times of the steam generators and other regulating components.

The system is adapted accordingly and optimized to yield best operation possible,

Schematic diagram of plants

Trip scenario

Pressure increase in main header due to small safety valve